Saul Ewing partner James Rohlfing recently published an article in the Summer 2026 issue of the e-magazine Substance about the importance of notices under construction contracts in Illinois and elsewhere.
Construction contract notice provisions are critical in recovering additional time or compensation for additional work. Notices are important when there are differing site conditions, design errors, delays, disruptions, and changes in scope. The article highlights that even imperfect notice is often better than no notice at all and emphasizes that notices can help resolve issues early, avoid misunderstandings, and strengthen a party’s negotiating position. Contractors and subcontractors can best protect their rights by documenting impacts, tracking deadlines, maintaining accurate records, and providing timely, contract-compliant notices in a professional and non-confrontational manner.